Our solar field
Every farm needs a field, so if we are about to be solar farmers, why not call it a “solar field”. With any luck, the installation crew will start Monday and I’ll be able to post some pics next week....
View ArticleSolar base installation [pics galore]
Today is Day One in construction of our solar power generation field. The first of three crews completed its work today – the “grounds” crew. Below is a photo essay of the job, with explanations. The...
View ArticleSolar Panel Installation [with photos]
The solar panels have arrived. And so have the installers. In fact, the solar panel installers have come and gone, leaving behind the almost-ready solar panels on their posts, ready to be hooked up to...
View ArticleSolar Electrical Installation [more pics]
The third and final solar installation crew has come and gone. There were three crews in total: Construction crew to dig, drill, pour the cement and erect the posts. Solar panel installation crew (to...
View ArticleMore solar installation details [with pics]
I have already detailed the three stages of our solar power generation installation, and here I will share a few extra details – some of the items left off in earlier posts. To recap, there were three...
View ArticleSolar Installation Timeline
Now that we are finally feeding the grid – yes, we are officially a solar power generation plant, providing electricity to all of Ontario! – let`s answer one of the burning questions that anyone...
View Article